For years, electricity costs for the Belden Brick Company in Sugarcreek, Ohio, had been relatively stable. Last year, they surged by 90 per cent – largely due to rising power demand from data centres in the region. The 141-year-old brick manufacturer, whose products can be found in iconic buildings including the Alamo in Texas and the University of Notre Dame, is seeing power bills rise mainly from a monthly capacity charge, which recently jumped from US$1,600 to US$12,000. Belden Brick is amo
is among many manufacturers across America’s heartland, where costs are rising as power-hungry data centres serving the artificial intelligence industry proliferate.
Factory electricity bills, a core expense, are rising faster than for many homes and other businesses, according to a Reuters review of US energy data and interviews with nearly a dozen manufacturers and industry advocates.
Federal, state and local governments, responding to consumer anger and concerns about grid stability, are pushing Big Tech to pay more for their expected demand. But some of their proposals lump smaller factories in with tech giants such as Meta and Amazon, whose power needs can dwarf those of even large manufacturers by a factor of 50.
Meta declined to comment. Amazon did not respond to a request for comment.
Capacity charges are designed to compensate power generators for ensuring the grid has enough electricity for peak usage and to spur the development of new supply. They generally account for about 10 per cent of residential bills but can represent up to three times that for manufacturers, according to interviews with manufacturers, attorneys and energy experts.
Such fees have soared in the 13-state region covered by grid operator PJM Interconnection due to stagnant supply and demand from data centres, where one server warehouse can use as much electricity as a mid-sized town.
“That capacity charge just jumped off the page,” said company president Brad Belden, part of the fifth generation working at the company.
Despite such capacity-charge hikes, PJM was forced to take emergency steps last week, including asking some users to curb electricity use, to prevent rolling blackouts as searing temperatures pushed peak demand to a new record.
The rising costs and regulatory uncertainty threaten the viability of some factories at a time when US President Donald Trump is prioritising domestic manufacturing, advocates and policy experts say. These businesses are considering raising prices, slowing growth or, in some cases, relocating.
Belden has raised brick prices by 4 per cent, and profits have still shrunk. If bills keep rising, he said, local manufacturers may quickly reach the limits of cost-cutting or price hikes.
“There are going to be some companies that are on the razor’s edge,” said Belden.
The White House said in a statement that Trump has taken action to cushion the blow for manufacturers, citing his hosting of tech companies signing a “ratepayer protection pledge” earlier this year and directives to build more power plants in PJM, paid for by tech companies.
Data centre advocates say the industry’s rapid expansion is driving long-overdue investments in America’s electric grid and cite other factors driving up costs, including power plant retirements and transmission constraints.
Data centre growth is “making us finally grapple with the difficult decisions that we were always going to have to face,” said Aaron Tinjum, vice president of energy for Data Center Coalition, a trade group.
A 1,000 per cent price increase
PJM, the largest US grid operator, covers a Mid-Atlantic and Midwest manufacturing belt from New Jersey to northern Illinois and as far south as Tennessee, which has become attractive to data centre developers.
Of the eight US states considered emerging data centre hubs, five are in the Rust Belt, according to Synergy Research Group data.
The clash of old manufacturers and new data centres in the same region weighs heavily on costs and grid reliability. Data centres, said PJM spokesperson Jeff Shields, can be built “faster than the generation needed to serve them, driving up demand faster than supply”.
PJM sets capacity prices paid to power generators based on forecast supply and demand, and manufacturers often pay an outsized share of those charges once they filter down to customers. PJM’s capacity prices jumped from $28.92 per megawatt-day in 2024 to the current $329.17 per megawatt-day – a 1038 per cent rise – driven primarily by data centre growth.
That helped push up electricity prices more quickly for industrial users in major manufacturing states that are also becoming data centre hubs in PJM’s region, according to Reuters calculations using US Energy Department data on electricity prices.
Average industrial electricity prices were up 31 per cent in Pennsylvania and 26 per cent in Ohio as of December 2025 from 12 months earlier, compared with a 7 per cent rise nationwide for industrial users. Residential customers in those two states saw increases of 14 per cent and 9 per cent, respectively.
Even a 1 per cent or 2 per cent increase in power costs can stretch factory owners, who often operate on thin margins and use large amounts of electricity, economists and industry officials say.
“This can have short- and long-term impacts on whether or not these facilities can continue to operate,” said Paul Cicio, president of the trade group Industrial Energy Consumers of America.
Graveyard shift
Capacity charges at plastic products manufacturer Plaskolite jumped to $1.2 million annually from $200,000 a year earlier at its combined Pennsylvania and Ohio facilities. The company is considering shifting from grid power to a direct natural gas feed for its operations, said Timothy Ling, Plaskolite’s senior environmental director.
“Electricity has become the highest-drama form of energy,” Ling said.
Grove City, Ohio-based Tosoh SMD, which produces materials used in electronics, is considering revving up production during the difficult-to-staff graveyard shift, when electricity is cheaper.
“We’re trying to be as creative as possible just to maintain competitiveness,” said John Holeman, Tosoh’s director of facilities and maintenance.
Protecting consumers, hitting manufacturers
Manufacturers are classified in the same electricity rate class as data centres, and they are being caught up in state and federal proposals aimed at shielding homes and small businesses from the price spikes tied to data centres.
Currently, very large energy users with their own onsite power generation in PJM pay transmission charges only for the power they draw from the grid. The Federal Energy Regulatory Commission is proposing that companies pay transmission charges for onsite power generation as well to ensure the grid has enough supply if onsite power fails.
Manufacturing advocates are appealing to FERC for exemptions. FERC declined to comment.
At least 10 US states also have pending rules to manage electricity demand from data centres, but their parameters could also affect manufacturers, according to data from the nonprofit Smart Electric Power Alliance and North Carolina State University’s NC Clean Energy Technology Centre.
“Manufacturers are not data centres,” said Cicio. “We should not be impacted by their effort to manage data centres.”
Belden and other manufacturers want Ohio’s regulators to scrutinise how utilities are estimating data centre electricity demand. Meanwhile, they’re trying to cut their own costs.
“You start to look at alternatives,” said Belden, who is thinking about installing onsite power generation to reduce reliance on the grid. “Manufacturing goes as power goes.”
Reporting by Laila Kearney in New York. Additional reporting by Tim McLaughlin in Boston and Jarrett Renshaw in Washington. Editing by Liz Hampton and David Gaffen. All courtesy of Reuters.